Service contract S2: Technical assistance for project supervision Contract commencement date: 10.03.2009...
Works contract CL12 – Water tanks and pumping stations in Cluj-Napoca Contract commencement date: 21.03.2012...
Procurement contract F3 – extension of SCADA system Contract commencement date: 16.01.2012 Contract period...
For the purposes of the project “Extension and rehabilitation of water and waste water systems in Cluj/Salaj counties” in the procurement plan from the application approved by the European Commission for co-financing the above mentioned project from the Cohesion Fund (2008 – 2012), a number of 20 contracts of services, procurement and works have been provided, of which: services: 2, procurement: 3, works: 14 ;